North Bend's River Park Runs On A Reimbursement Clock, Not A Construction Calendar

October 1, 2026

Drive past the riverfront on a random Tuesday and you might see three earthmovers parked and idle for a week straight, then a paving crew laying asphalt from dawn to dusk for four days running. The fencing around the 14-acre site south of the William Henry Harrison Tomb has been up long enough that some neighbors stopped noticing it. Others assume the project stalled.

Neither read is quite right. The William Henry Harrison Riverfront Park is being built the way it's being paid for: in bursts, tied to when the state sends a check back.

A volunteer engineer runs the schedule

The person who has spent the most hours on this project doesn't work for the village. Skip Holmes is a retired Procter & Gamble engineer and North Bend resident who took on the unpaid role of project manager, assembling a community advisory group and coordinating with the landscape architecture firm KZF Design and the wayfinding firm Brownstone Design to turn a flood-prone stretch of riverbank into something usable.

Holmes told council he planned to step down as project manager effective January 1, 2026, after seeing the project through its construction phase. That handoff matters for anyone trying to read the pace of work from the road. A single person who has carried a project's institutional memory for years does not transfer that knowledge instantly, and a schedule that depended on his availability to chase reimbursements and manage contractor relationships was always going to look different once someone else picked it up.

The money moves in reimbursements, not a lump sum

Here is the part that explains the stop-and-start pattern better than anything about weather or contractor availability. The primary funding source is an Ohio Department of Natural Resources grant, and Holmes described the mechanics of it plainly in a council session: the village submits invoices for completed work, and the state typically sends reimbursement back in roughly three weeks. That sounds fast until you consider that the village has to front the cash first, on a municipal budget sized for a village of roughly 835 residents.

When the numbers got tight, council authorized a $225,000 advance to cover contractor bills while waiting on state reimbursement, on top of an earlier request for a revolving cash line to handle monthly invoices. By that point the village had already fronted and been reimbursed for $85,138 in pre-construction costs, with a $10,000 donation from the Duke Foundation and Hamilton County CDBG revitalization funds layered in alongside the ODNR grant. Every one of those funding streams runs on its own timeline. A grading contractor doesn't wait for a state reimbursement cycle, but the village's ability to pay the next invoice sometimes does.

That's why the visible work comes in waves. Earthworks contractor J and D Rack Excavating priced its portion of the job at $232,500, and once that contract clears, the crews show up and move fast until the scope is done. Then paving contractor JK Muir Paving takes over for base asphalt and resurfacing under a separate council resolution, and there's another gap while invoices route through the reimbursement pipeline before the next phase can start. None of this is mismanagement. It's what building a park with grant money looks like when the entity doing the building is a village government, not a developer with a construction loan sitting in reserve.

What the six phases actually cover

The full plan breaks into six phases, and only some of them have visible construction underway. The first covers a new road, site grading, and opening general access to the river. That's most of what residents have watched happen through 2025 and into 2026: earthwork, drainage, the beginnings of a walking trail.

Two later phases are the ones that will change what the park is actually for. A kayak and canoe launch is planned for the eastern corner of the site, giving paddlers a formal put-in on a stretch of the Ohio River that currently has none nearby. At the western end, a parking area and pavilion are planned as the venue for concerts and community events, the piece of the project most likely to become a regular fixture on the village calendar rather than something you drive past.

The remaining scope includes an event and interpretive center and a pedestrian bridge, both of which sit further out on the six-phase sequence. A council update in the fall of 2025 noted that stream restoration and site grading were nearly complete for that phase of work, with closeout targeted for early December of that year. Whether the interpretive center and bridge follow on a similarly tight schedule depends on the same reimbursement rhythm that's shaped everything before it.

The park keeps the sewage plant and the railroad, on purpose

Most riverfront redevelopment tries to hide the industrial stuff. This one doesn't. A working sewage treatment plant sits in the middle of the property, part of the Metropolitan Sewer District's network, and a rail line cuts across it. Rather than screen those features off, the design incorporates them into the interpretive trail, with signage planned to explain both the environmental story of wastewater treatment and the historic role rail played in the region's commerce.

It's an unusual choice for a park meant to also honor a presidential burial site immediately to its north, but it fits the site's actual character better than pretending the infrastructure isn't there. The 60-foot obelisk marking William Henry Harrison's tomb has stood next to this land the entire time the property sat as an overlooked collection of river camps and homemade docks. The park doesn't erase what came before it. It builds around it.

The village didn't do this alone

North Bend's plan connects to something larger than its own 14 acres. Holmes has been in contact with Great Parks, Hamilton County's park system, and with Ohio River Way, an organization working to link roughly 40 small towns along a 274-mile stretch of the Ohio River into a connected trail network. If that regional effort keeps moving, North Bend's riverfront becomes one link in a chain that extends well past Hamilton County, not an isolated destination.

That regional ambition got institutional recognition in 2026, when the Hamilton County Regional Planning Commission awarded the village its Frank F. Ferris II Community Planning Award for the riverfront park masterplan, honoring Mayor Doug Sammons alongside years of phased planning work. Awards like this don't finish a construction schedule, but they signal that the county's planners see the project as a model worth naming, not just a village vanity build.

What to expect if you're watching from your porch

If you live close enough to hear the earthmovers, the practical takeaway is this: gaps in visible activity aren't a sign the project has quietly died. They're the reimbursement clock doing what it does. Contractors bill for completed work, the village submits to the state or county, and roughly three weeks later money comes back that lets the next phase start. Big visible pushes, like the asphalt work that ran under Resolution 2025-18, tend to follow right after a funding gap closes.

With Skip Holmes handing off day-to-day management at the start of 2026, whoever takes the project forward inherits a partially built road and grading network, an earthworks contract largely executed, and four remaining phases that depend on the same grant cycles that got the project this far. The kayak launch and the pavilion are the two pieces most likely to change how the site actually gets used once they're in place. Until then, the fencing and the occasional idle excavator are just what mid-construction looks like on a public project that pays its bills after the fact instead of before it.

If you're weighing what a home near this stretch of the river will actually be worth once the park is finished, Michele Donovan Group knows North Bend well enough to walk you through it property by property.